Fort Bend ISD approves construction of new elementary school, questions emerge

During a series of public comment and Board of Trustee meetings, parents, employees and taxpayers of the Fort Bend Independent School District were presented with the plan for a proposed bond package on the November 2014 ballot. The presentation included a plan to construct ES 46 in Aliana, a facility needed to address overcrowding at Oakland Elementary.

With unissued but authorized debt from a 2007 bond election, Superintendent Dupree emphasized to the community the District has the $32.3 MM in funds (page 20) necessary to proceed with construction of ES 46 and on August 11, 2014 the Board of Trustees voted to move forward with construction of the much needed school.

Say what??

In a May 2013 Board of Trustee meeting (scroll to the 2:54:00 mark) the Board was told an evaluation team examined nine proposals to build ES 46 with Pepper Lawson announced as the best value for the District. The Pepper Lawson bid came in at $14.8 million– $300,000 over the original construction budget back in 2007 of $14.5 million.

Max Cleaver told the Board Pepper Lawson could make the 365 day construction schedule to complete the school by August 2014.

One month later in June 2013 at the urging of Dr. Dupree, the Board ultimately voted to wait for the completion of the Long Term Facilities Plan before approving the contract to construct ES 46.

Fast forward to August 2014

According to an August 11, 2014 agenda packet, Superintendent Dupree had previously been delegated the authority to execute the Guaranteed Maximum Price (GMP) amendment to the contract if the cost was $18,147,517 and the board voted for issuance of a $20,638,774 guaranteed maximum price (GMP) contract (Item 6A) for the construction of ES #46 in Aliana with an 11- month construction schedule.

ES 46’s constructions costs have increased from $14.8MM in May 2013 to $18.1 MM in August 2014—an increase of 22{997ab4c1e65fa660c64e6dfea23d436a73c89d6254ad3ae72f887cf583448986} over 16 months.

Questions emerge

The Board approved construction of ES 46 however questions have emerged–Fort Bend ISD taxpayers want to know if a GMP contract to construct ES 46 in time for an August 2015 opening date would typically contain a premium of 22{997ab4c1e65fa660c64e6dfea23d436a73c89d6254ad3ae72f887cf583448986}.

Over a six-year period, the cost to build ES 46 increased by $300,000 yet between May 2013 and August 2014 construction of ES 46 has grown by another $3.3 MM—an increase of over 22{997ab4c1e65fa660c64e6dfea23d436a73c89d6254ad3ae72f887cf583448986}.

Are vendors taking advantage of Fort Bend ISD taxpayers?